Open meganhicks opened 1 week ago
Created a template on the Mural above to help organize our planning; to work with @meganhicks before the end of the sprint to add any other tasks, questions, and considerations based on the information we have at this time.
The Enablement Team, along with partner teams (CC, EE, BIE, BIP, and LHDI), has requested a timeline of events to complete all activities related to decommissioning the VRO platform. This will allow them to plan their contributions to help VRO wind down the platform and reorganize the team effectively.
Acceptance Criteria:
Develop a timeline that clearly lists activities and projected sprints to complete each task. Ensure the timeline includes defined milestones from Mural, such as shutting down EPMerge, migrating Max CFI, migrating CC, etc. Share the timeline with the team and seek alignment.