Closed bischoffa closed 6 months ago
Closing out this epic given Q1 is over and moving tickets to other epics - 8305, 8364, 6761
Several tickets remained. Team had planned time to work on tickets however found they were pulled into non QA work (unplanned / unexpected / bigger than sized) so less work than expected was completed.
Project Status Overview
Project Objective:
Current Dependencies / Blockers
Blockers
|Blocker | Team / Owner | Est to Resolution | |-------|---------|-------| | DevOps hire needed | Mobile | TBD | | PR automation to support e2e testing needs pre-production | Mobile | TBD | | |Project Timeline
Milestones
|Step | Timing | |-------| ---------| | DevOps onboarding | | |Automation Catch-Up | | |Internal Documentation Readiness | | |External Documentation Readiness | | |Internal Policy Readiness | | | 100% Release | | |Step 4 - Post Verification| |Monthly Update for Stakeholders
Updates
|Month| Project Health | Progress & Key Accomplishments| Issues/Risks/Blockers| |-------| ---------|--------|---------| |January 2024 | Green | Inclusion into Q1 2024 planning | |Month Year| ..... |Month Year| |Month Year|Detailed Project Scope
Problem Statement
OCTO Goals Supported
Assumptions
Assumptions that need to be true for this project
1.) External team integration not planned for Q1 2024 2.) 3.)Risks
Risks identified and accepted by stakeholders
1.) External teams integration with mobile to be pulled in before team is prepared 2.) DevOps hire is delayed - delaying work and release prep needs 3.)Definition of Done
Conditions that must be true in order to consider this project completed
- Internal team enablement - External team has onboarded successfully and completed QA / Release on a major featureImportant Project Links
Links
- Github Epic= 7624 - [Team's Github VA Mobile Page](https://github.com/department-of-veterans-affairs/va.gov-team/tree/master/products/va-mobile-app/Teams/QA%20and%20Release) - Analytics - [Decision Log ](https://github.com/department-of-veterans-affairs/va.gov-team/blob/master/products/va-mobile-app/Teams/QA%20and%20Release/Decision%20Log.md) - [Policies ](https://github.com/department-of-veterans-affairs/va.gov-team/tree/master/products/va-mobile-app/Teams/QA%20and%20Release/Policies) - [Processes](https://github.com/department-of-veterans-affairs/va.gov-team/tree/master/products/va-mobile-app/Teams/QA%20and%20Release/Processes) - [VA Mobile Docs QA section](https://department-of-veterans-affairs.github.io/va-mobile-app/docs/QA/)Team Members
Contact List
**VA:** - **Mobile OCTO Product Leads:** Rachel Han or Ryan Thurlwell **Ad Hoc:** - **Mobile Team**: QA - **Mobile Team Lead:** Adam Kasmier - **FE Engineering:** NA - **BE Engineering:** NA - **Design:** NA - **Content** NA - **QA:** Therese, Tom, and Rachael - **Mobile Teams that are involved:** Global, Health and Benefits, Design System, QA, APIOKR and Analytic Metrics
Analytic Information
**What KPIs / OKRS are the focus of this project?** Ideas: 1.) Change failure rate - hotfixes, rollbacks 2.) Number of bugs and their severity 3.) Time to repair / detect 4.) PR review time |What we are measuring | Why | How / Event Name | |-------| ---------| ----- | | How will we determine this is a success? | | | | How will we determine if this is not a success? | | | |Analytic Event| What is it measuring | How to use it to measure | |-------| ---------| ----- | | | | | | |Questions
Open Questions
- How are we measuring success? - What is MVP and what is out of scope? - Has there been existing research or work done on this project before? - Is this work being done within the VA today (ex. web)Closed Questions
| Question | Answer | Owner | |--------|----------|------| | | | | | | | |