Project Status Overview

Project Objective:

This epic is focusing on Accessibility related work for the VAHB during Q3. This would include accessibility needs on top priority items in Design System, Flagship, and Global. While also include general technical debt and maintenance of Accessibility needs. This work will include:

At least 30% will be allocated specifically todays Accessibility Technical Debt while the other 70% can be used to support Flagship, Design System and H&B or UX floater needs.

Accessibility work that other projects or teams require will fall under their specific project's epic and not here. This epic is specifically for internal Accessibility work.

Stakeholder Updates

Date Project Health Progress & Key Accomplishments Issues/Risks/Blockers
9/30/2024 Green MCAG documentation (turning presentation into official documentation) is underway. Tickets have been created and working through general documentation. None
9/16/2024 Green Review of past audit tickets to update severity is complete. None
9/16/2024 Green Dark / light mode color audit is complete. None
9/16/2024 Green Recommended updates for alert announcements have been determined and discussed with the design system team. None
9/4/2024 Green MCAG presentation complete. None
8/19/2024 Green Project steps have been properly outlined and accessibility artifacts have been integrated into the steps. Implementation of these steps will be covered in a future ticket. None
8/19/2024 Green Project steps have been properly outlined and accessibility has been integrated into the steps. Implementation of these steps will be covered in a future ticket. None
8/19/2024 Green Worked with Adam and Therese to integrate accessibility into our bug severity. Will create a new ticket to update the issue severity guide on the documentation site with these additions. None
8/6/24 Green Regained access to TestFlight to test iOS accessibility issues. Defined Q3 priorities. Preparing for MCAG materials for the next Mobile Demo. Reviewing Steps process and defining artifacts and requirements Accessibility wants to have at each step. Incorporating Accessibility findings into bug severity process and documentation None

OKRs

- Stability - Reduce Accessibility bugs by 25% - Productivity - Enable teams to build faster through accessibility best practices, artifacts, and expectations - Retention - Improve Veteran retention amongst Veterans with Accessibility Needs (meet WCAG / MCAG standards) - Satisfaction - Improve Veteran satisfaction amongst Veterans with Accessibility Needs (ensure Accessibility is MVP)

Risks

Risks - Capacity continues to be pulled away from Accessibility specialist toward other areas like UX - Accessibility (standards, code, reviews) not being deemed a requirement or show stopper for releasing new features or changes to features - Perception that Accessibility work does not need to be reviewed by an Accessibility specialist before going into production

Assumptions

Assumptions - Accessibility needs and testing is just as critical as QA - Capacity will only be used for Accessibility related work - Non Accessibility related work will eventually be moved to the appropriate group of people

Current Dependencies / Blockers

Blockers |Blocker | Team / Owner | Est to Resolution | |-------|---------|-------| | Internal dependency ? | | | External dependency ? | |

Team Members

Contact List **VA:** - **Mobile OCTO Product Leads:** Rachel Han or Ryan Thurlwell - **VA OCTO Product Leads:** - **External Team 1 & Role:** - **External Team 1 & Role:** - **Ad Hoc:** - **Mobile Team**: Qart - **Mobile Team Lead:** Adam - **FE Engineering:** NA - **BE Engineering:** NA - **Design:** Brea - **Accessibility** Brea - **Content** NA - **QA:** Therese, Tom, Rachael - **Mobile Teams that are involved:** Global, Health and Benefits, Design System, Qart
bischoffa commented 3 months ago

Presented on 7/24 to POs during Q3 Planning Review. POs approved to move forward with this. No questions or concerns from the POs on this epic.

TKDickson commented 1 week ago

Q3 work completed; closing epic.