This is hard to verify because CAISO doesn’t clearly specify what is under construction and I don’t know how accurate date_proposed_online is. I filtered our gridstatus data on is_actionable and date_proposed_online < 2025 and got 19 GW.
GS data includes projects up to 3/2/2023, whereas the LBNL data includes data up to 7/7/2022. The differences could be explained by changes in the queue between 7/22 and 3/23. To do a fair comparison, we could wait until CAISO and LBNL interconnection queue data is updated.
In the meantime, some action items could be:
Reach out to Synapse or CAISO to better understand the difference between CAISO's two interconnection reports.
Reach out to LBNL to see when they plan to release new data
NY onshore vs offshore wind
CAISO changes
date_proposed_online