Some checklist items are incomplete, and the Initial Operational Capacity milestone is not met. We agree to invest additional work toward this milestone, then hold another review in 2 weeks.
(Picking up Fall semester) Some checklist items are incomplete, and the Initial Operational Capacity milestone is not met. We agree to invest additional work toward this milestone, then hold another review in 2 weeks.
3 Issue by smattingly,
Two to three weeks into the Construction phase, all success-critical stakeholders should meet and try to come to agreement on the following points.
We agree that the work products captured in this repository ...
Check the box for each item that is endorsed by all stakeholders. Then create a comment on this issue to document the outcome of the review. The comment should contain one of these three possible outcomes.
If appropriate, set the due date of the IOC milestone for 2 to 3 weeks in the future, when the next stakeholder review will take place.