eclipse-tractusx / sig-release

https://eclipse-tractusx.github.io/sig-release
Apache License 2.0
6 stars 6 forks source link

Deadlines for R24.08 KIT and FOSS #682

Open tom-rm-meyer-ISST opened 1 month ago

tom-rm-meyer-ISST commented 1 month ago

@tom-rm-meyer-ISST is going to ask @hfocken about deadlines:

We're currently wondering about the deadlines for releases in R24.08 for

HFocken commented 3 weeks ago

Hi Tom & team,

thanks for reaching out and apologies for not commenting sooner! For the KITs I can already answer since we had communicated that early on in an Association OpSync:

KIT Release Guideline • 3 weeks prior to the Release, Initial Pull Request (11.7.) • 1 week prior to the Release, Final Pull Request (25.7.) • KIT-Release as part of the Tractus-X Release (1.8.)

For testing, I'll have concrete dates by tomorrow morning I hope!

tom-rm-meyer-ISST commented 3 weeks ago

Hi Tom & team,

thanks for reaching out and apologies for not commenting sooner! For the KITs I can already answer since we had communicated that early on in an Association OpSync:

KIT Release Guideline • 3 weeks prior to the Release, Initial Pull Request (11.7.) • 1 week prior to the Release, Final Pull Request (25.7.) • KIT-Release as part of the Tractus-X Release (1.8.)

For testing, I'll have concrete dates by tomorrow morning I hope!

Thanks for pointing out @HFocken!

Are further deadlines (testing, qgate) for FOSS software releases beside the final release date already known?

HFocken commented 3 weeks ago

Additional deadlines for FOSS are:

Feature Freeze / Kick-off e2e Test: 14.06.2024 Test Freeze: 21.06.2024 Release Freeze: 5.7.2024

There are no separate Q-Gates besides the TRGs as this is no longer a consortium release and we have transfered most of the Q-Gate criteria either into certification or the TRGs.

mhellmeier commented 3 weeks ago

Thanks for the deadlines! It might make sense to use the GitHub Milestone functionality to track the process.

One addition question:

• 3 weeks prior to the Release, Initial Pull Request (11.7.) • 1 week prior to the Release, Final Pull Request (25.7.)

@HFocken : What is the difference between an "Initial Pull Request" and a "Final Pull Request"? Do you mean creating a pull request and waiting for the reviews (-> initial) after it will be merged (-> final)?

tom-rm-meyer-ISST commented 6 days ago

@HFocken As FOSS deadlines come closer: Do we have updates or some kind of coordination in place for INT test? We also would like to use the environment to quickly show the application to persons who are interested into our reference implementation.

cc: @Clemens-L-Schwarz @PhillipNalesny @Ute-Burkhardt-Volkswagen