Closed GoogleCodeExporter closed 9 years ago
This will be added to 1.1
Original comment by shlomyga...@gmail.com
on 28 Nov 2008 at 5:58
i have added the quarterly view of chart, each quarter of 3 months. its working
fine
but the placement of the bar is not always right. I will be obliged if you can
help
in that. I am attaching the file.
Original comment by khurram...@gmail.com
on 1 Dec 2008 at 8:08
Attachments:
I was not setting the minimum date and maximum date according to quarter view.
i have
fixed it now. attaching the new version. Still start point of the bar is a
little
behind the expected place. i.e if the starting point of a task May 10, it should
start from Quarter 2 but it starts from Quarter 1 in chart. Can anyone please
help me
in this problem (I have removed the left columns that were not needed in our
project).
Original comment by khurram...@gmail.com
on 2 Dec 2008 at 8:00
Attachments:
I have fixed the positioning of the bar in quarter view. It is working, although
don't know if this is the right way or not. any comments and suggestions will be
appreciated.
Original comment by khurram...@gmail.com
on 3 Dec 2008 at 1:00
Attachments:
Quarterly view has been implemented in the R12 .. you can download the up to
date
code from the SVN trunk
Original comment by shlomy%b...@gtempaccount.com
on 11 Dec 2008 at 8:00
Original comment by shlomyga...@gmail.com
on 11 Dec 2008 at 8:04
Original issue reported on code.google.com by