Copy of a Work Order that is completed, with est and actual costs per measures.

Report per: Work Order Existing ReportID: 16 Generated by: Agency

eckmanwe commented 6 months ago

See Work Order Report.

fishbaugher commented 6 months ago

Bill, thank you, yes, the work order report is pretty well complete. One thing that is really nice is the implementation of the measure comment area here. I explorig the limits of the work order measure comment field and I found:

1) There is clearly more than 256 characters allowed here (nice). 2) The editor box on the form has enough lines where it is readable/usable. 3) White space is preserved. 4) The whole comment fields and its white space are carried forward to the report in a vertically expanding comment area.

All four of these features would be wonderful if it applied uniformly throughout WAweb and its reports!

Only one problem remains for this report. It would appear that while the estimated total is shown in the economic summary are, the actual cost total is not. Here is the equivalent 8.9 report with totals shown for both estimated and actual:

Untitled

while it would appear that the v10 work order report only shows the estimated:

Untitled2