When creating a multi-level BOM in the BOM Creator, the costs are not calculated up the tree. The below example illustrates:
Expected: Grand Total: (12 £150.64) + (10 59.756) = £2405.24
Actual: £210.396
manufacturing
ERPNext: v15.22.2
None
No response
@rohitwaghchaure ?
Information about bug
When creating a multi-level BOM in the BOM Creator, the costs are not calculated up the tree. The below example illustrates:
Expected: Grand Total: (12 £150.64) + (10 59.756) = £2405.24
Actual: £210.396