kltm commented 10 months ago
Project link

https://github.com/orgs/geneontology/projects/149

Project description

The purpose of this project is to increase the number of releases (snapshot and release) made and decrease the amount of time per release attempt. While a complete pipeline refactor may be in the cards in the future, this project is aimed at, more or less, "working with what we have".

To this end, the focus will be:

PI

Chris

Product owner (PO)

Pascale

Technical lead (TL)

Seth

Other personnel (OP)

TBD

Technical specs

No new libraries or technologies. The only "interesting" additions would likely be:

Other comments

N/A

kltm commented 10 months ago

@pgaudet I have a note that says that this can be considered under way (lit. "move to working"); does that sound right to you?

kltm commented 10 months ago

@pgaudet confirms above.

kltm commented 3 weeks ago

@kltm believes that the remainder can be folded into the GOC / GOA pipeline project, as the work here is not completely informed or dependent decisions in that project.

kltm commented 3 weeks ago

closed; remaining tickets moved to https://github.com/geneontology/project-management/issues/93 https://github.com/orgs/geneontology/projects/159