Projected Date | Actual Date | Task | Ticket(s) |
---|---|---|---|
02 April | 02 April | Dataset plan | #1184 |
05 April | 05 April | Data Downloads | #1193 |
10 April | 16 April | Pre-processing (including misc data edits) | #1201, #1217 |
~15 April~ 18 April | 19 April | Provide datasets to Nathan | #1249, #1252 |
~22 April~ 26 April | 30 April | Nathan's export ready | |
~26 April~ 29 April | 01 May | Pre-processing of glycan data | #1285 |
~29 April~ 02 May | 04 May | Data processing (Robel) | #1208 |
06 May | 10 May | QC datasets | #1243 |
07 May | 10 May | Push API and Front end to tst | |
~09 May~17 May | BCO creation & edits | #1206 | |
17 May | Finish testing tst - Phase I | ||
23 May | Finish testing tst & Beta release | ||
30 May | Finish testing on beta | ||
31 May | Production release |