Establishing team velocity and estimating effort #3820

Closed SeamusLeonardHPE closed 3 weeks ago

SeamusLeonardHPE commented 1 month ago

Establishing team velocity • Creating analytics to measure velocity is important. • It would enable accurate planning and predictability based on the team's story-point throughput. • It may take 5-6 sprints to establish the team's velocity.

Estimating effort for tasks • Sizing tasks using the story points method is recommended. • There is a question about whether effort should be estimated in days or hours.

julauxen commented 4 weeks ago

Figjam file: https://www.figma.com/file/5LPziU19w4TdMQ9CN4Evq0/Team-Velocity?type=whiteboard&node-id=0%3A1&t=2EjsxRNt1TnuGcQ7-1