Closed StevieeeLau closed 9 months ago
Task 9.1 to create the black-box test cases and task 9.2 to verify the test cases have been completed. Task 9.3 to evaluate the test case results is completed as well to update into the M3 report through task 9.4, thus overall task is accomplished.
Work has been committed to report.
Work was completed on time.
No changes to success or completion criteria of task.
Start and End date: 7/11/23 - 11/11/23.
Work done, issue closed.
Task Title ID: 9
About this task: To create and confirm the black box testing diagram.
Goal: To create and confirm the details of the black box testing into the M3 Report.
The success criteria: When the review of the black box testing is deemed completed and updated into the M3 Report.
Allocated Time: 4 days.
Start and End date: 6/11/23 - 9/11/23.
Owner: Steven.
Status: Refer to GitHub status.
Priority: High.