Task Title ID: 11

About this task: To complete the prototype.

Goal: To input the details of the prototype into the M3 report.

The success criteria: When the information of the prototype is reviewed and deemed appropriate and placed into the M3 report.

Allocated Time: 6 day.

Start and End date: 14/11/23 - 19/11/23.

Owner: Cassandra.

Status: Refer to GitHub status.

Priority: High.

StevieeeLau commented 9 months ago

Task 11.1 to create the prototype and task 11.2 to review the prototype have been completed. Task 9.3 to create the video demonstration with the prototype is completed as well, thus overall task is accomplished.

Work has been committed to report.

Work was completed on time.

No changes to success or completion criteria of task.

Start and End date: 15/11/23 - 21/11/23.

StevieeeLau commented 9 months ago

Work done, issue closed.