M1 Retrospective: What to commit to #37

Open AstralAurora opened 10 months ago

AstralAurora commented 10 months ago

What has been done in M1 that can be brought to M2, values, good things etc.

StevieeeLau commented 10 months ago
  1. M1 Report's introduction and project scope, can be carried forward to M2.
  2. Software Requirements are done well, therefore there isn't a need to bring them forward to M2.
Cassandra-Fu commented 10 months ago

i. M1 software requirements no change ii. M1 Use Case Diagram must be updated and improved to be carried forward to M2 Diagrams. iii. Work Break Down Structures need to broken down futher into smaller and more specific tasks. iiii. Work Delegation in Kanban Board needs to be more systematic and clear to everyone.

hanz105 commented 10 months ago
EvanChua22 commented 10 months ago