Closed StevieeeLau closed 10 months ago
The lifeline elements, trace messages and focus of control for the sequence diagram done in tasks 6.1 to 6.3 were reviewed. The overall sequence diagram has updated into M2 Report.
Work has been committed to report.
Work was completed on time.
No changes to success or completion criteria of task.
Start and End date: 12/10/23 - 13/10/23.
Work done, issue closed.
Task Title ID: 6.4
About this task: To review, finalise the lifeline elements, trace messages and focus of control and update the overall sequence diagram into the M2 Report.
Goal: To update the sequence diagram into the M2 Report.
The success criteria: When the review of the sequence diagram is deemed completed to update into the M2 Report after a review.
Allocated Time: 2 days.
Start and End date: 12/10/23 - 13/10/23.
Owner: Ng Teng Hui.
Status: Refer to GitHub status.
Priority: High.