7.4 Update Component Diagram to M2 Report #48

Closed StevieeeLau closed 10 months ago

StevieeeLau commented 10 months ago

Task Title ID: 7.4

About this task: To review, finalise the component notation, interface notation, and ports and delegates of the component diagram and update the overall component diagram into the M2 Report.

Goal: To update the component diagram into the M2 Report.

The success criteria: When the review of the component diagram is deemed completed to update into the M2 Report after a review.

Allocated Time: 2 days.

Start and End date: 22/10/23 - 23/10/23.

Owner: Ng Teng Hui.

Status: Refer to GitHub status.

Priority: High.

StevieeeLau commented 10 months ago

The component notation, interface notation, ports and delegates of the component diagram done in tasks 7.1 to 7.3 were reviewed. The overall component diagram has updated into M2 Report.

Work has been committed to report.

Work was completed on time.

No changes to success or completion criteria of task.

Start and End date: 22/10/23 - 23/10/23.

StevieeeLau commented 9 months ago

Work done, issue closed.