5.4 Update Class Diagram to M2 Report #49

Closed StevieeeLau closed 10 months ago

StevieeeLau commented 10 months ago

Task Title ID: 5.4

About this task: To review, finalise the attributes, methods and the relationships of the classes and update the overall class diagram into the M2 Report.

Goal: To update the class diagram into the M2 Report.

The success criteria: When the review of the class diagram is deemed completed to update into the M2 Report after a review.

Allocated Time: 2 days.

Start and End date: 02/10/23 - 03/10/23.

Owner: Hannah Leong.

Status: Refer to GitHub status.

Priority: High.

StevieeeLau commented 10 months ago

The attributes, methods and relationships of the entity, control, boundary classes done in tasks 5.1 to 5.3 were reviewed. The overall class diagram has updated into M2 Report.

Work has been committed to report.

Work was completed on time.

No changes to success or completion criteria of task.

Start and End date: 02/10/23 - 03/10/23.

StevieeeLau commented 9 months ago

Work done, issue closed.