Closed StevieeeLau closed 9 months ago
Tasks 10.1 to 10.3 have been reviewed and have updated the white-box testing into M3 report.
Work has been committed to report.
Work was completed on time.
No changes to success or completion criteria of task.
Start and End date: 14/11/23 - 15/11/23.
Work done, issue closed.
Task Title ID: 10.4
About this task: To enter the information of the white box testing into the M3 report.
Goal: To input the details of the white box testing into the M3 report.
The success criteria: When the review of the white box testing is deemed completed and updated into the M3 Report.
Allocated Time: 1 day.
Start and End date: 13/11/23 - 13/11/23.
Owner: Teng Hui.
Status: Refer to GitHub status.
Priority: High.