1) skipping a day: Using the site today - June 9, when the day preselects is set to "does not matter", the first event that shows up on the events page is for June 10, which is ok.

When I change the day preselects to "next 3 days" or "next 7 days" the first event that shows up is for June 11, so it skips a day for some reason.

2) weekend to include friday: option for "upcoming weekend" should include the upcoming friday. For now, we can just include day "friday", but we will see if we have too many morning shows coming up in results for friday, if yes, we might have to cut down on time (like starting at 4pm friday or something).

romasolot commented 10 years ago

Fixed, already on http://hashplans.com/user/events/all

hashplan commented 10 years ago

2) from above seems to be fixed, I see the weekend includes the friday.

1) is not. Setting the day preselect to next 3 days or next 7 days seems to skip the next day. Right now I am looking at all events, which starts the list showing events on June 30, when I set day preselects to next 3 or next 7 days, it starts showing events starting July 1.

romasolot commented 9 years ago

how many days should I finally include to the selection? "Next 3(7)" days means today + 3(7) days = total 4(8) or Total 3 ( 7 ) days, I mean today + 2 ( 6 ) days ?

hashplan commented 9 years ago

second case, so if I am filtering right now, I want to see next 3 days show - July 3, 4, 5 and next 7 days to show July 3-9

romasolot commented 9 years ago

Fixed, already on http://hashplans.com

hashplan commented 9 years ago

Doing a filter on Atlanta metro area events today (July 8) for next 3 days returns data for July 8, 9, 10 and 11.

Seems like it is adding a day on the back. It should not return July 11th.

romasolot commented 9 years ago

Fixed