Phase 2 focuses on the full migration of the Non-Production environment, dependent on the successful completion of Phase 1. During Phase 1, the deployment, provisioning, and validation of the new Non-Production environment will have been completed. Phase 2 will build on this foundation to carry out the actual migration process.
Note: Phase 2 can only proceed only if the results of Phase 1 are deemed successful.
Intended Outcome
Complete migration of all Non-Production secrets.
Establish processes and prerequisites for issuing new certificates using the new PKI.
Ensure certificates issued by the old PKI remain functional until their expiration.
Decommission the existing Non-Production environment.
Out of Scope
The Production environment is not included in this phase.
Impact on Teams
Some level of disruption is expected as teams transition to using the new Vault environment. Efforts will be made to minimise disruption, but the extent will only become clear after the completion of Phase 1.
DTSPO-22468
Summary
HashiCorp Vault - Phase 2: Non-Production Migration
Phase 2 focuses on the full migration of the Non-Production environment, dependent on the successful completion of Phase 1. During Phase 1, the deployment, provisioning, and validation of the new Non-Production environment will have been completed. Phase 2 will build on this foundation to carry out the actual migration process.
Note: Phase 2 can only proceed only if the results of Phase 1 are deemed successful.
Intended Outcome
Out of Scope
Impact on Teams
Some level of disruption is expected as teams transition to using the new Vault environment. Efforts will be made to minimise disruption, but the extent will only become clear after the completion of Phase 1.