Closed brunomac closed 6 years ago
@brunomac , can you be more specific? A screenshot or an example on how to reproduce it would be great.
ie. On the first project approach the project started on Jan and finished on Nov. On the current baseline (after replan and client agreement), the first task is on Jun and the last on Sept. The EVM aggregated chart continues to show the start date on Jan and the project finishing on Nov, but the charts it self only goes from Jun to Sept.
Attached chart/image has different dates, but the problem is the same.
Hi @brunomac
I've tested this based on the given example and it seems to be working as expected.
Thanks
EVM aggregated chart is considering tasks initial and end dates from issues that don't belong to selected Version