CSAT would like to have workplan based on historical data built and visualized. However, when WP would start, workplan should be amended with actual data exported from AMOS, available now on FTP.
Example: TASK 291000-20-1-600 planned on Friday 1.1.2021. Actually performed on Monday the forth. The blue "rectangle" would be erased
CSAT would like to have workplan based on historical data built and visualized. However, when WP would start, workplan should be amended with actual data exported from AMOS, available now on FTP. Example: TASK 291000-20-1-600 planned on Friday 1.1.2021. Actually performed on Monday the forth. The blue "rectangle" would be erased