WHAT - There are three stormwater sites in concept design that fall along I-695 in the same location as an ongoing highway widening project until 2019. Stormwater sites that are part of the project are in the same location.
CONFLICT - CTP
SITE NAMES
BA-GRP1-MTI-038
BA-GRP1-MTI-037
BA-GRP1-MTI-040
BA-GRP1-MTI-039
BA-GRP1-MTI-041
ACTION NEEDED - Consultant must be notified to remove sites from their concept package
Data has been updated in the TMDL database on 04//23 to "ON HOLD" and conflict points have been created in the PLANNING_CONFLICTS featureclass. This issue issue will be closed as soon as the consultant has been notified.
WHAT - There are three stormwater sites in concept design that fall along I-695 in the same location as an ongoing highway widening project until 2019. Stormwater sites that are part of the project are in the same location.
CONFLICT - CTP
SITE NAMES BA-GRP1-MTI-038 BA-GRP1-MTI-037 BA-GRP1-MTI-040 BA-GRP1-MTI-039 BA-GRP1-MTI-041
ACTION NEEDED - Consultant must be notified to remove sites from their concept package