After estimation of size is determined through Use Case Points, estimation of effort would also be done via the range of estimation of hours for each UCP: 15 to 30 hours. The estimated effort in developer-hours of a project of size 450 UCP falls between 15 UCP to 30 UCP (in hours). Hence, Estimation of Effort would be below.
15 82.11065 to 3082.11065 = 1232 to 2463 hours
After estimation of size is determined through Use Case Points, estimation of effort would also be done via the range of estimation of hours for each UCP: 15 to 30 hours. The estimated effort in developer-hours of a project of size 450 UCP falls between 15 UCP to 30 UCP (in hours). Hence, Estimation of Effort would be below. 15 82.11065 to 3082.11065 = 1232 to 2463 hours