Closed kittiu closed 4 years ago
Sorry, I posted this while I was editing. I am updating this.
@kittiu Please see the explanation form the readme of the analytic_plan modules. It will help you to understand: https://github.com/ForgeFlow/eficent-odoo-addons/blob/12.0/analytic_plan/README.rst https://github.com/ForgeFlow/eficent-odoo-addons/blob/12.0/analytic_resource_plan/README.rst
As a summary:
Hope this helps you to understand a bit.
Regards.
@AaronHForgeFlow , Is this correct?
@AaronHForgeFlow , Is this correct?
- Planned Cost and Revenue comes from Project Bids
You can create them form the bids, or by hand, normally you only use one source of planned costs.
Ps: confirming resource plan lines will also generate analytic.plan.line, but those will go to a different planned version, so they are not mixed with the created ones from other sources.
- Planned Resource comes from what we create in project's Resources
Yes, normally it is used just for planning material resources.
- And to trigger PO and MO is only from this project's Resources, correct?
Yes, only from resources. Actually, they will create just "demand" like sales order do. They do not create PO and MO directly. The project manager have to go every day to the MRP application and see what it is needed.
Great! a lot more cleared now. Thanks!
Thank you! I'm glad to help.
I see these objects many place, still not capture what it is, How is it related to account.analytic.line?