The following tasks are required to complete onboarding for an Incubation level project joining the LF AI & Data Foundation. LF Staff will engage with the technical project lead via this issue and work through the checklist to completion.

LF AI & Data Staff: Review each item, confirm completion, and add any relevant notes.

Note: (ED) Executive Director, (Tech) Technical Lead, (PM) Program Management & Operations Lead, (Mktg) Marketing Lead

TECHNICAL PROJECT DETAILS

--Maturity Level Proposed: Incubation --Company Sponsor (Full Legal Name): University of California Berkeley --Jurisdiction of Incorporation: USA --Address: 2030 Addison Street, Berkeley, California 94704 --Project Sponsor Contact: Ion Stoica --Technical Contact: Simon Mo --Legal Contact: --TAC Sponsor: Ion Stoica --TAC Approval Date: 7/11/24 --Project License: Apache 2.0 --Project Presentation: URL to presentation --Project Proposal per LF AI & Data: n/a --Project Artwork: https://github.com/lfai/artwork/tree/main/projects/vLLM

LICENSING

CONTRIBUTION

PROJECT ASSETS

TAC & GOVERNING BOARD REVIEW

INFRASTRUCTURE

OPERATIONS

GOVERNANCE

MARKETING

LEGAL FOLLOW UP

NSouthernLF commented 1 month ago

@jeffcshapiro this needs intake and foss scans set up. thanks.

jeffcshapiro commented 1 month ago

@NSouthernLF I should be able to do this next week, although I do have a lot of pending intake scans for other project so it could be a bit longer - let me know if there is any schedule urgency.

I don't see an entry in your tracking spreadsheet yet, let me know when you've added it there.

NSouthernLF commented 1 month ago

Thanks @jeffcshapiro - it was literally just approved yesterday so we're just now starting to onboard. Timing wise it would be helpful to get it done in the next 2-3 weeks. Doable?

jeffcshapiro commented 1 month ago

@NSouthernLF 2-3 weeks should be OK

NSouthernLF commented 1 month ago

Invited simon-mo, WoosukKwon and zhuohan123 to LFAI GH to add them to this issue.

Also: emailed Simon Mo as the chief contact to set up a 30m onboard call with him.

NSouthernLF commented 1 month ago

Landing page ticket submitted 7/22/24

NSouthernLF commented 1 month ago

@cakerly-lf we need your help on the 4 marketing items above. thanks.

NSouthernLF commented 1 month ago

Nathan and Nancy spoke at length with Simon Mo for 30m 7/30/24 and noted the following as part of onboard:

-the project is asking for AWS credits, as its monthly cloud costs total > $50k and they are looking to bring this down. Nancy sent them the application for this and we clarified that 50 is a large ask - will see what can be done. For now this has been updated in the onboarding spreadsheet and AWS above is marked done.

-The project needs no additional collaboration tools (marked done above) -The project does not desire a wiki space at this time (marked done above) -The project is not conducting public meetings at this time (only internal) but is interested in doing LFX meeting management with a public calendar once the charter is signed. For now this is left unchecked above. -The project has one key social media platform - in the form of Twitter/X. Simon wishes to have an alias created, wants to be added, but prefers to specify the others via an email with Nathan. Nathan emailed him to ask for names/addresses 7/30/24, and added him to alias vllm-social@lfaidata.foundation. -For now a Jira ticket has been filed extending CM/scheduler access to the whole vLLM team. -Nancy also re-requested an ETA for the final charter - Simon gave us an ETA of approximately 1 month - late Aug '24.

NSouthernLF commented 1 month ago

Emailed Simon, Woosuk and Zhuohan, sent them https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/create/144 And requested the transfer of the vllm.ai website 8/1/24

NSouthernLF commented 4 weeks ago

Simon wrote back today to indicate that their website transfer ticket has been filed.

NSouthernLF commented 4 weeks ago

Regarding charter: Nancy and Nathan spoke with Simon on 7/30 who estimated 3-4 weeks for finalization. it is working its way through their legal team.

NSouthernLF commented 3 weeks ago

No public meetings requested at this time.

NSouthernLF commented 2 weeks ago

Followed up via email on vLLM charter with Ion, Simon Mo and the team on 8/14/24 - to check on the status and see if we can help expedite. Their last update was on July 26th.

NSouthernLF commented 1 week ago