What is the task about? This task involves the updating of User Interface Requirements that were highlighted in the feedback from M1.

What are the goals of the task? The goal is to ensure that the documentation is updated with the changes that were made to the product's User Interface requirements.

Success or Completion Criteria: All necessary changes have been documented in the report.

Allocated time: 3 days

Start date and end date: [Start Date: 16/10/23], [End Date: 18/10/23]

Owner: Alain

Status of the task: To-Do

Priority: Medium

ImUrGit commented 11 months ago

Describe the work done in detail: I have placed the changes that were revised for the user interface requirements in the M2 report.

Has this work been committed to the repository? No, there is no need to commit this work to the repository as it is done on the project board.

How does the work affect success or completion criteria? The work done has made it easier to document and make it easier fro those who are reading what were the changes from M1 to M2.

Start Date: 16/10/23, End Date: 18/10/23