[2.1.3] Change in Use Case Diagram #127

Closed Magic1sarap closed 11 months ago

Magic1sarap commented 11 months ago

What is the task about? This task is to revise changes to the requirements from the M1 report. Thus, the team's use case diagram would have to be revised as well.

What are the goals of the task?

Success or completion criteria:

Allocated time: 4 days

Start date and end date: [Start Date: 18/10/23], [End Date: 21/10/23]

Owner: Isaac

Status of the task: To-Do

Priority: Medium

Magic1sarap commented 11 months ago

Describe the work done in detail. The changes were done according to the M1 feedback.

Has this work been committed to the repository? No, as there was no code involved.

How does the work affect success or completion criteria? Corrects the use case diagram for a more accurate representation of the system for the stakeholders.

Start date and end date:

[Start Date: 16/10/23] [End Date: 28/10/23]