"major upgrade to include LSST DR1 into the Sherlock classification algorithm. Inclusion of gravitational wave skymaps – for the LIGO-Virgo-Kagra O5 run (projected Oct 2025). Finalised information flow from 4MOST spectroscopic survey."
Subsequently in Aug'23, the Lasair Long Term Plan defined it as
D3.5.4 = Lasair 7 (PM70=Apr 2025) Real time processing and services for the LSST alert stream. Inclusion of gravitational wave skymaps – for the LIGOVirgo-Kagra O5 run (projected Oct 2025). Finalised information flow to and from 4MOST spectroscopic survey.
Subsequently, given changes to the Rubin Operations schedule, change request CR107 altered the deliverable scope to be
a review of the integration of optical survey data and multi-wavelength triggers (Fermi, IceCUBE); a major upgrade to the Sherlock classification algorithm by adding LSST deep drilling catalogs; inclusion of gravitational wave skymaps – for the LIGO-Virgo-Kagra O5 run (projected Oct 2025); finalised information flow from 4MOST spectroscopic survey.
This is a Phase C deliverable.
According to Phase C proposal, it comprises
Subsequently in Aug'23, the Lasair Long Term Plan defined it as
Subsequently, given changes to the Rubin Operations schedule, change request CR107 altered the deliverable scope to be