Create WP3.5 six month plan for Oct'22 to March'23
#52
Closed
tms-epcc
closed
2 years ago
tms-epcc
commented
2 years ago
Topics to consider when updating this 6 month plan
[x] in plan to Sept'22 in terms of organisation, practices and procedures
what worked well?
what did not work well?
what can we improve?
what should we keep?
what should we drop?
[x] Review the
WP Brief
are any updates required?
[x] Review the associated
SRD requirements
[x] Review risks
Is any escalation required?
Are there risks for those tasks/ tickets/ dependencies, … on the critical path?
[x] Create Zenhub epic for next six months
[x] create tickets for latest 6 month objectives if necessary
[x] Shift any outstanding tickets from previous plan if appropriate
[x] Close previous 6 month plan Epic kanban
[x] close tickets, remove duplicates as necessary
[x] Include Rubin in-kind reporting requirements
[ ] Identify any WP 3.5 task/ milestone/ deliverable dependencies with other LSST:UK WP tasks.
Note any such dependencies on relevant Kanban tickets
[ ] Is there sufficient effort available for all the chosen tickets?
Move tickets to stretch if necessary
Is effort still a concern after updating stretch?
tms-epcc
commented
2 years ago
16/SEP/22
review of past 6 months, brief, SRD and Risks took place, see minutes for meeting on WP3.5 wiki page
tms-epcc
commented
2 years ago
11/OCT/22
following WP-PM meeting on 07/OCT/22, this can be closed
Topics to consider when updating this 6 month plan
Is effort still a concern after updating stretch?