Corresponds to M2 in inkind workplan google doc
Means of verification : originally
wish the WP3.6 software to be ready to run with the commissioning data.
this will involve taking the simulated data at that time and checking that it produces outputs that are useful
BUT
Note :
The 23/AUG/23 Executive Group meeting approved this change request C077 to alter the title, scope and due date of milestone MS33 from “End of Science Readiness/ Commissioning” on 31/DEC/23 (PM54) to “Submission of Science papers on D3.6.2 (D2) and D3.6.3 (D4)" on 31/MAR/24 (PM57).
The 25/MAR/24 Executive Group meeting approved change request C096 that changed title and scope to “Submission of Science paper on D3.6.2 (D2)" on 31/MAR/24 (PM57).
The software associated with this milestone (i.e. D3.6.2 (D2) and D3.6.3 (D4)) need to be ready by the time real data
comes through hence the milestone is currently aligned with the end of commissioning phase. Unfortunately, the
end of commissioning is currently expected DEC'24 so now need to submit a change request to alter the title to relate to "Submission of Science papers on D3.6.2 (D2) and D3.6.3 (D4)" and move the due date to end of Mar'24.
The 23/AUG/23 Executive Group meeting approved this change request C077 to alter the title, scope and due date of milestone MS33 from “End of Science Readiness/ Commissioning” on 31/DEC/23 (PM54) to “Submission of Science papers on D3.6.2 (D2) and D3.6.3 (D4)" on 31/MAR/24 (PM57).
agreed that with the submission of D3.6.2 (#19) for DESC internal review, this Exec group can be asked to approve the milestone being marked as passed.
Corresponds to M2 in inkind workplan google doc Means of verification : originally
BUT Note :