Closed lzim closed 5 years ago
Thanks for this detailed timeline and deliverables @lzim -- Jane and I are meeting tomorrow.
So far so good with Prod 1.7. I have run some experiments for PSY, and I am really liking the interface. I got confused with some experiment naming/documenting, so I will try to clean that up and rerun. Then I will try to finish the SAY file experiment table.
Hello Everyone!
RELEASE Schedule - Going from MTL 1.6 to MTL 1.7 for inclusion in MTL Video. 📆
As a culmination of all our progress to date, in the next 60 days, we have 2 major Team PSD Milestones with our key partners: frontline staff, OMHSP and EES
Below are the point people from the 6 Team PSD Workgroups completing the MTL 1.7 Release in time for the MTL Video Shoot in St. Louis the week of 11/26/2018:
At our Team PSD workgroup meetings with this week, we decided on our immediate NEXT Steps for the MTL 1.7 release, which adds the ”Measurement-based Stepped Care for Suicide Prevention" module through a phased final development review process with OMHSP and Frontline Stakeholders.
STEP 1 MTL 1.6.1: Schedule stakeholder consensus meeting week of 10/1/2018
DECISIONS DUE: 10/5/12018
KEY STEP 1 Team PSD dependencies (3 workgroups - 4 action steps):
STEP 2 MTL 1.6.2: TeamPSD Workgroups develop MTL resources to support Stakeholders' Decisions
WORK DUE: 10/12/2018
Key STEP 2 Team PSD dependencies (4 workgroups):
STEP 3 MTL 1.6.3: Stakeholder consensus meeting week of 10/15/2018 DECISIONS DUE: 10/19/12018
KEY STEP 3 Team PSD dependencies (4 workgroups):
STEP 4 MTL 1.6.4: Team Achieves Standardization for UI-Freeze based on Stakeholders Final Recommendations for what would support their decisions
WORK DUE 10/26/2018 - MTL 1.7 UI Freeze - EES Master Brochures for MTL 12-session plan to EES
KEY STEP 4 Team PSD dependencies (6 workgroups):
STEP 5 MTL 1.6.5: Go from Development -> Test - MTL 1.7 available in Test
WORK DUE 11/2/2018
KEY STEP 5 Team PSD dependencies (3 workgroups):
STEP 6
WORK DUE 11/9/2018
1. MTL 1.7 available in Production 2. MTL learner SEE and facilitator SAY files for SP Module completed
KEY STEP 6 Team PSD dependencies (3 workgroups):
STEP 7 MTL 1.7.1 - SP Rehearsals for MTL Video Shoot in St. Louis
WORK DUE 11/16/2018 KEY STEP 7 Team PSD dependencies (2 workgroups):
----Step 8 will be minor tasks and relaxing with friends and family over the holiday---- ----Then we have the MTL Video Shoot in St. Louis the week of 11/26/2018----