Risk creation date: 8/26/2023

Last Modified: 8/26/2023

Risk type: Scientific Impact

Risk Approach: Mitigate

Risk Owner: Jared Males

Risk Statement:

If GMagAO-X cannot secure the funding needed to maintain schedule, other instruments might be developed at other observatories that can perform as well or better than GMagAO-X.

Risk Effects:

GMagAO-X is trying to achieve the best performance possible with today's technology. However, as technology advances, we can expect future instruments to exceed the capabilities of GMagAO-X. This means that GMagAO-X has a limited window of opportunity to achieve a strong science impact. To maximize the GMagAO-X science mission, we need to complete the instrument development on schedule, and we need to take advantage of any opportunities to get on sky early (see #22).

Risk Assessment:

Risk Ratings Likelihood Consequence
Initial 3 3
Current 3 3
Target 1 2

Initial Risk Notes: We need about $6M to procure the suite of DMs needed for GMagAO-X. The lead time for these items is 2-3 years. If we determine that we need 5 microns stroke, the cost will be around $12M and the lead time 3-5 years. To hold schedule, we need to order the DMs pretty soon after the December 2023 PDR. We likely need to be ordering other long lead items in 2024.

Risk Notes/Updates:

Cost Impacts:

Estimated cost if risk is realized:

Explanation for cost risk:

Risk mitigation list:

- [ ] Secure funding sufficient (around $10M) to procure long lead items in 2023-2024 - [ ] - [ ] - [ ]