Open marcusbory opened 2 years ago
Downgrade & Non-acceptance:
The interchangeable use of task
and event
is clear to the user in the given context.
Team chose [response.Rejected
]
Reason for disagreement: I opine that the interchangeability of the two terms task
and event
is only clear to the developers. Since the developers wrote the User Guide, they already have a preconceived notion of what they are referring to in this context, but it may not be as apparent to the end user, especially first time users.
This may cause confusion that there exists another period of time, especially since it was not stated in the glossary that the terms are interchangeable (refer to below, if screenshots for justification are allowed in Phase 3 of PE):
Team chose [severity.VeryLow
]
Originally [severity.Medium
]
Reason for disagreement: Since the average user is likely to glance quickly at the user guide if they do not face any problems, they are unlikely to find these inconsistencies.
However, if they are found, there can be confusion caused, especially since first time users may not be familiar with the terms.
Since there are minor inconveniences caused in certain scenarios, I believe that the revised severity level should be severity.Low
, instead of the downgraded severity.VeryLow
.
Expected: For personal usage, a user will refer to those periods of time either as
events
ortasks
Actual: There appears to be a discrepancy in the UG regarding this. Example shown below.
Description of
Add an Event to timetable
Description of
Delete from timetable