Remaining website work #28

Closed eli4 closed 8 years ago

eli4 commented 8 years ago

all website materials can be found here: https://github.com/maryi/CSCW-Project/tree/master/Development/Web/turorial

Third: (this one can be done at any point) we need to decide how we want the search function to want IE how we are going to pick which results to recommend.

kristalow commented 8 years ago

here's an idea of what the website could look like with a header & stuff example

mpaskevi commented 8 years ago

That look great @kristalow! What do you think @eli4 and @dustinfaulkner91, possible to style the site this way?

eli4 commented 8 years ago

its 100% possible and I suspect it wouldnt take very much work to get it looking like this.

mpaskevi commented 8 years ago

Hi @dustinfaulkner91 @eli4 , I am seeing some differences between the app as it currently exists and our description in the project report document? See https://github.com/maryi/CSCW-Project/blob/master/Project%20report/ReportDocument.md#11-explanation-of-user-requirements for the latest fields described for search and register an app.

What are the chances we could bring the app in line with our report? If its not possible before Friday we should have an explanation of why its not the same and our plan for deployment.

mpaskevi commented 8 years ago

@eli4 I am seeing that you have addressed this issue in the report just now. So I am guessing it is not feasible for Friday?

eli4 commented 8 years ago

there is a chance that ill have time to add this image to the html either tonight or tomorow afternoon. It depends on how fast I can finish some of my other school assignemnts. Otherwise maybe @dustinfaulkner91 could add it in when he is modifying the fields in the register and search page

mpaskevi commented 8 years ago

@eli4 @dustinfaulkner91 it would be great! if it does get done please be sure to update the report as well. we want to be sure our report matches our current prototype.

dustinfaulkner91 commented 8 years ago

We're more focused on functionality at the moment. Making it pretty is easy enough after everything works properly. We may need to modify some descriptors for functionality's sake.

mpaskevi commented 8 years ago

Hi team, how is the application development going? I am hoping we can begin some user testing this week. Is there an estimate on when we might have the app in line with our latest document?

eli4 commented 8 years ago

i was planning on implementing a possible search function today which is the only missing functional component. however the way the html was giving data was inconsistent with the list of base applications we have so i have to sort that out before doing the search function. hopefully i will still have time today to do both. after that all thats left is to make it look pretty and perhaps improve the search function if necessary

eli4 commented 8 years ago

at the current rate of things it looks like in less than three hours, the website should have search functionality! from that point on there should only be minor modifcations needed, for example adding links on all the pages to the home page

mpaskevi commented 8 years ago

It looks like the app search page is out of sync with the current report document. Is this the most up to date version of the app: http://turorial1-1120.appspot.com/search? It is missing purpose which is supposed to a multi-select dropdown, likewise for domains of practice. See: https://github.com/maryi/CSCW-Project/blob/master/Project%20report/ReportDocument.md#11-explanation-of-user-requirements

eli4 commented 8 years ago

that is the current version of the app. Dustin is for the most part in charge of the html so i guess he is still working on that part. realisticly I would expect it to only be around an hour of work to add those features at most. If Dustin is busy and cant get around to adding those features I can try and do that as well i suppose but i might not be able to do it today.

dustinfaulkner91 commented 8 years ago

I'm on it, I've been busy up until now.

eli4 commented 8 years ago

alright dustin has now added the purpose field and i have implemented a search function, you can now test out the search function at: http://turorial1-1120.appspot.com/search. Hopefully now all major components of the website are done and we will just need to do a few minor tweaks.

mpaskevi commented 8 years ago

Nice progress guys! @eli4 I can not see your new search function, perhaps put it in another location as the /search page is currently for describing cscw work. We could also change that page name to /describe

I have found a few small things to change on the app. Is there a way I can adjust the text? Are the source files currently on GitHub?

Thanks!

maryi commented 8 years ago

Same here.. I want to help with the development :) @eli4 @dustinfaulkner91 Where can I find the source files?

eli4 commented 8 years ago

all the files are under development/web/turorial, if you want to change the text ull want to edit the searchIndex.html and registerIndex.html files

eli4 commented 8 years ago

@mpaskevi when you go to http://turorial1-1120.appspot.com/search and file out that survey and hit submit does it not return search results for you?

maryi commented 8 years ago

There is still this question when searching for an app: How many different areas of study is your team involved in?... This is communities of practice dimension, which was replaced by Domains. I presumed this was taked from the mockups, remember that those are out of date. Check the report to get more info.

maryi commented 8 years ago

Same thing when registering an app. The question :How many different areas of study can the application support is about the communities of practice, which was also replaced by Domains Check the report.