"in RDE on the Start Date field, it now accepts incomplete date info and then
errors whatever was put in to a valid date equalling the day you created the
record ie if I type in 4/10 (for April 2010) I think the old version used to
lock you in that field till you gave it an acceptable date ie 4/2010. Now, if I
type in 4/10 this version accepts the change but errors it to ie 29 Jun 2011
and lets you proceed with entering information. Can we please fix this so that
the date details have to be acceptable before you can move out of the field?" -
from Robyn
Original issue reported on code.google.com by david.ba...@gmail.com on 30 Jun 2011 at 1:09
Original issue reported on code.google.com by
david.ba...@gmail.com
on 30 Jun 2011 at 1:09