Task title ID: 2.3.3.2.2 Sequence Diagram (CASE 5). Task: Create a Sequence of Diagrams focusing on use case 5 for M2. Goals: Complete a sequence diagram (use case 5). Success or completion criteria: A completed Sequence Diagram on use case 5. Allocated time: 18 days Start date: 11 Oct End date: 28 Oct Owner: Weichen Priority: High

LeeWeiChen2200810 commented 11 months ago

i. A Sequence diagram has been created focusing on one of the 2 most prominent use cases which in this case is use case 5. ii. The work has been committed to the repo. iii. The work done follows the success criteria of having a completed sequence diagram. iv. The start date is 11 Oct and the work is completed by 27 Oct.