Closed LeeWeiChen2200810 closed 11 months ago
i. Update the user interface requirements based on the M1 report feedback. ii. The work has been committed to the repo. iii. The work done follows the success criteria of having the requirements for user interface will be much clearer. iv. The start date is 22 Sept and the work is completed by 27 Sept.
Task title ID: 2.3.2.2 User Interface Requirements. Task: To list the user interface requirements based on the feedback for the M1 report. Goals: To add the part to complete the M2 report. Success or completion criteria: Complete this section for the M2 report. Allocated time: 2 days Start date: 26 Sept End date: 27 Sept Owner: Weichen Priority: High