Task title: 2.3.4.2 Updated Use Case Task: The task is to recreate a new Use Case diagram and recreate a new Use Case Description to be used in upcoming diagram creation. Success or completion criteria: Complete the task by creating the two items which are the Use Case diagram and the Use Case Description. Allocated time: 19 day Start date: 22 Sept End date: 10 Oct Owner: Darshan Priority: High

DarshanKumar-SIT commented 11 months ago

i. Both the Use Case diagram and the Use Case Description have been created. ii. The work has been committed to the repo iii. The work done follows the success criteria of having a completed the Use Case diagram and the Use Case Description. iv. The start date is 22 Sept and the work is completed by 10 Oct