Closed JunHianL closed 11 months ago
1) The pilot figma and report section has been completed without any delays. 2) The work has been committed to the repo. 3) The work done follows the success criteria of having a completed pilot figma for the prototype and the report writing for the section. 4) The start date is 29 Oct and the work is completed by 21 Nov.
Issue/Task Details Task title ID: 3.2.4.2 Pilot. Task: Create the pilot prototype and complete the report section. Goals: Create the pilot prototype figma for the M3 prototype and complete the report section. Success or completion criteria: Successful creation of pilot prototype figma and complete the report section. Allocated time: 24 days Start date: 29 Oct End date: 21 Nov Owner: Jun Hian Priority: High