Closed mechproz closed 10 months ago
1) Observation design pattern and comparisons has been added to the report. 2) How does the work affect 4. success or completion criteria. 3) Task is completed. 4) Start and End Date of the work done. Start date: 3/11/23 End date:8/11/23
Task title ID: 3.2.2.2.2 Observer. Task: Compare design patterns similar to observer and determine if Observer is best for this project. Goals: The goals are to understand the different design patterns and evaluate them against the Observer design pattern. Success or completion criteria: the above criteria is met and the Design pattern segment of the M3 report is filled. Allocated time: 6 days Start date: 3 Nov End date: 8 Nov Owner: James Priority: Low