Data needed to complete schedule for Hydra WirelessHart project #14

Closed Ezrael2979 closed 9 years ago

Ezrael2979 commented 9 years ago
kevinmershon commented 9 years ago

I will try to answer all 3 here. All figures workdays:

Deliverables

  1. Wireframe sketches of UI
    • sequence id: 1
    • assignee: Darin
    • status: complete
    • estimated duration: 5 days
    • actual duration: 1 day
  2. Prototype Ionic app utilizing Cordova plugins with Hydra and Mershon Enterprises branding
    • sequence id: 1 (overlaps into 3+)
    • assignee: Darin
    • status: in progress
    • estimated duration: 10 days
    • actual duration: 2 days (as of 3/6)
    • notes: Darin would work faster on this, but he's waiting on the plugins to be completed, branding/logos to be provided, and is trying to be considerate of the burn rate on the project since this is Overhead work
    • dependencies: to really complete this, all the plugins and all the menus and screens have to be finished
  3. Prototype Cordova plugin for manipulating WiFi connection state
    • sequence id: 2
    • assignee: Cris
    • status: in progress
    • estimated duration: 4 days
    • actual duration: 3 days (as of 3/6)
    • notes: Cris thinks he's nearly done on this
  4. Prototype Cordova plugin for collecting data from a WirelessHART gateway
    • sequence id: 2
    • assignee: Kevin
    • status: in progress
    • estimated duration: 7 days
    • actual duration: 2 days (as of 3/6)
    • notes: I prototyped the gateway comms to make sure we can even do the project. Today I stubbed out the Cordova plugin to get used to how plugins work, and am going to be working on the Android version of the gateway driver the week of 3/6
  5. Prototype Cordova plugin utilizing Estimote SDK to identify nearby beacons
    • sequence id: 3
    • assignee: Cris
    • status: not started
    • estimated duration: 5-10 days
    • notes: Cris aims to start on this as of 3/6
  6. Implementation of UI menus
    • sequence id: 2
    • assignee: Darin
    • status: in progress
    • estimated duration: 2 days
    • actual duration: 1 day (as of 3/6)
    • notes: Darin has already implemented the menus, but they don't really have functionality until the plugins are finished and integrated
  7. Implementation of Transmitter List screen
    • sequence id: 2
    • assignee: Darin
    • status: in progress
    • estimated duration: 2 days
    • actual duration: 1 day (as of 3/6)
    • notes: Darin has already implemented this screen using mock data, but live data will require refreshing and other nuanced considerations we are not yet able to verify
    • dependencies: this is dependent on the WirelessHART plugin
  8. Implementation of Mesh Overview screen
    • sequence id: 3
    • assignee: TBD
    • status: in progress
    • estimated duration: 5 days
    • actual duration: 1 day (as of 3/6)
    • notes: Darin has already implemented a placeholder screen for this which is just blank. @kevinmershon will probably be writing this
    • dependencies: this is dependent on the WirelessHART plugin
  9. Implementation of Transmitter View screen
    • sequence id: 3
    • assignee: TBD
    • status: in progress
    • estimated duration: 5 days
    • actual duration:
    • dependencies: this is dependent on the WirelessHART plugin
  10. Implementation of Transmitter Trend screen
    • sequence id: 3
    • assignee: TBD
    • status: in progress
    • estimated duration: 5 days
    • actual duration:
    • dependencies: this is dependent on the WirelessHART plugin
kevinmershon commented 9 years ago

For this project, assume "1 day" means 4 hours for me, 8 hours for Cris, and 2 hours for Darin, depending on who is working the task.

kevinmershon commented 9 years ago

@Ezrael2979 Let me know if you need any other details. :smile: