Logistics project 桩基 40 基础 50 钢构 60 机电 90 消防验收 30 竣工验收 30
Process: Design - Procurment - Construction - Test & commission
Duration of logistics project: 8 months - 12 months Most likely 10 months
Logistics project 桩基 40 基础 50 钢构 60 机电 90 消防验收 30 竣工验收 30