@faiza-a this issue is the pre-requisite to your assigned issue. Once this is completed we'll set up a time to discuss the design with you for the submission portal.
@emileyfadrosh @dehays wanted to make sure you coordinate. This issue is currently assigned to Emiley. @dehays if you're working on the requirements please let me know and let me know if this issue should be re-assigned to David or anyone else.
Will get to this after the NAR paper is submitted on Sunday. Unless I am mistaken, no action is needed from @dehays.
Compiled the three separate requirements docs, and put together a straw man outline for input from the team: https://docs.google.com/document/d/1w-1ObkcIJUZ-iUB0RqB_wsM5TzOMfTa2Sta1MF2A07I/edit?usp=sharing
Would appreciate input from @kfagnan @pvangay @mslarae13 @cmungall @turbomam @wdduncan @dehays @ssarrafan
Shared above document and discussed with team, further implementation details will be worked out for September sprint.
This is step 7 of Goal 2 for the July sprint.
Define the scope of the submission site (Emiley, Pajau, Montana)