A Gantt chart is a type of bar chart which illustrates a project timeline or schedule. The Gantt Chart visual shows the Tasks, Start Dates, Durations, % Complete, and Resources for a project. The Gantt Chart visual can be used to show current schedule status using percent-complete shadings and a vertical "TODAY" line. The Legend may be used to group or filter tasks based upon data values.
Other
118 stars 114 forks source link

Issue with collapse/group bars #160

Closed ferdinand2020 closed 5 years ago

ferdinand2020 commented 5 years ago

Hi,

I like the new update! But i have experienced that if task with a couple of legends grouped together where two of the legends has same start date, then only one of them is visualized, where i expect to see both, since one of them has a higher duration than the other, and therefore will continue afterwards.

Please see attached screenshot and test power bi file, where you can see the issue on Project 1 with the legend Project and Phase 1. Phase 1 is not showing due to same start date as Project legend.

Hope you will fix this.

Screenshot 2 Screenshot 1 Test Data.zip

ferdinand2020 commented 5 years ago

Hi,

Any idea when this bug will be fixed, I have a customer that really need this very soon?

helen508light commented 5 years ago

This issue is in work now. There is no ETA, but in the most optimistic plans it could reach prod after 3 weeks

ferdinand2020 commented 5 years ago

Hi Elena,

Thanks for your answer, I have been away for vacation. I could see you expect 3 weeks to be in prod from your answer, so I assume that will be in this week, is this something I can rely on still? 😊

Med venlig hilsen/Best regards [cid:image001.png@01D55BE2.D7A10C10] Peter Ferdinand Bruun[cid:image002.png@01D55BE2.D7A10C10]https://www.linkedin.com/in/peter-ferdinand-jensen-45148346/ Team Lead & Senior PPM Consultant p: +45 60 21 58 14 m: pfj@projectum.commailto:pfj@projectum.com w: www.projectum.comhttp://www.projectum.com/ [cid:image002.png@01D55BE2.D7A10C10]https://www.linkedin.com/company-beta/121947/[cid:image003.png@01D55BE2.D7A10C10]http://www.projectum.dk/en/about/sign-up-for-our-newsletter/[cid:image004.png@01D55BE2.D7A10C10]https://www.youtube.com/channel/UCPiCGv62HWH9L8kxWtFjlGw[cid:image005.png@01D55BE2.D7A10C10]http://www.projectum.dk/en/news/

From: Elena Rodionova notifications@github.com Sent: 7. august 2019 12:13 To: microsoft/powerbi-visuals-gantt powerbi-visuals-gantt@noreply.github.com Cc: Peter Jensen pfj@projectum.com; Author author@noreply.github.com Subject: Re: [microsoft/powerbi-visuals-gantt] Issue with collapse/group bars (#160)

This issue is in work now. There is no ETA, but in the most optimistic plans it could rich prod after 3 weeks

— You are receiving this because you authored the thread. Reply to this email directly, view it on GitHubhttps://github.com/microsoft/powerbi-visuals-gantt/issues/160?email_source=notifications&email_token=AMSNQDIGVQGZEX7ZZP3MW5DQDKN3XA5CNFSM4H7OWXD2YY3PNVWWK3TUL52HS4DFVREXG43VMVBW63LNMVXHJKTDN5WW2ZLOORPWSZGOD3X5MDI#issuecomment-519034381, or mute the threadhttps://github.com/notifications/unsubscribe-auth/AMSNQDJIJPFF23BAGBCWTDDQDKN3XANCNFSM4H7OWXDQ.

helen508light commented 5 years ago

@ferdinand2020 I told about the most optimistic option... We had added this issue to your backlog, but there is no ETA for now

ferdinand2020 commented 5 years ago

Hi Elena

Thank you for the quick answer.

Med venlig hilsen/Best regards [cid:image001.png@01D55BFF.D556A0B0] Peter Ferdinand Bruun[cid:image002.png@01D55BFF.D556A0B0]https://www.linkedin.com/in/peter-ferdinand-jensen-45148346/ Team Lead & Senior PPM Consultant p: +45 60 21 58 14 m: pfj@projectum.commailto:pfj@projectum.com w: www.projectum.comhttp://www.projectum.com/ [cid:image002.png@01D55BFF.D556A0B0]https://www.linkedin.com/company-beta/121947/[cid:image003.png@01D55BFF.D556A0B0]http://www.projectum.dk/en/about/sign-up-for-our-newsletter/[cid:image004.png@01D55BFF.D556A0B0]https://www.youtube.com/channel/UCPiCGv62HWH9L8kxWtFjlGw[cid:image005.png@01D55BFF.D556A0B0]http://www.projectum.dk/en/news/

From: Elena Rodionova notifications@github.com Sent: 26. august 2019 11:14 To: microsoft/powerbi-visuals-gantt powerbi-visuals-gantt@noreply.github.com Cc: Peter Jensen pfj@projectum.com; Mention mention@noreply.github.com Subject: Re: [microsoft/powerbi-visuals-gantt] Issue with collapse/group bars (#160)

@ferdinand2020https://github.com/ferdinand2020 I told about the most optimistic option... We had added this issue to your backlog, but there is no ETA for now

— You are receiving this because you were mentioned. Reply to this email directly, view it on GitHubhttps://github.com/microsoft/powerbi-visuals-gantt/issues/160?email_source=notifications&email_token=AMSNQDJ6QA7S4RDD2N2WHD3QGONGXA5CNFSM4H7OWXD2YY3PNVWWK3TUL52HS4DFVREXG43VMVBW63LNMVXHJKTDN5WW2ZLOORPWSZGOD5DZUYY#issuecomment-524786275, or mute the threadhttps://github.com/notifications/unsubscribe-auth/AMSNQDII6D2VHH4TL672BODQGONGXANCNFSM4H7OWXDQ.

helen508light commented 5 years ago

Hi, @ferdinand2020 We had investigated this question. Actually, it is not an issue. U use the same Project Name and the same Start, but don't use Task name(needed for difference). Legend field is not used in grouping. Rows can be grouped by such fields: Task, Parent, StartDate, Resource, ExtraInformation, Milestones.

So, there are no difference between this 2 rows for power BI, because in this visual used grouping by category(Task field and Start Date in your case).

You may use parent-child structure: Task field is Task name and Parent field is Project Name. But it has different picture(one row for pre child) The second way is DAX Queries usage - u can merge 2 fields in one(Task Name + Project Name) and the use this merged field to achieve your goal