A Gantt chart is a type of bar chart which illustrates a project timeline or schedule. The Gantt Chart visual shows the Tasks, Start Dates, Durations, % Complete, and Resources for a project. The Gantt Chart visual can be used to show current schedule status using percent-complete shadings and a vertical "TODAY" line. The Legend may be used to group or filter tasks based upon data values.
Other
112 stars 103 forks source link

Formatting settings revert to default when a slicer is applied #215

Open bleow opened 3 years ago

bleow commented 3 years ago

More information here: https://community.powerbi.com/t5/Desktop/Keep-formatting-settings-after-a-slicer-filter-is-applied/m-p/1172761#M528840

bleow commented 3 years ago

After some testing and experimenting I've come to the conclusion that the milestone formatting settings take reference / inherit from the formatting settings of the project in the last row.

A(n ugly) workaround hence exists in the form of 1) Appending a dummy project to your real data 2) Sorting the visualisation such that the dummy project appears as the last in the list 3) Reminding users to check the dummy project in the filter whenever they use it

image Formatting options reset

image Enabling the dummy project (called "Sample VIEW" in my case) in the filter for the projects to inherit formatting settings from

Hope this has helped in your debugging in some way