Project Plan #1

Closed abhineet97 closed 4 years ago

abhineet97 commented 4 years ago

This is my project plan. Each section below represents a Milestone/Deliverable. Under each section is a list of tasks that must be completed for the milestone/deliverable to be considered achieved/delivered.

This is a living document and hence will be updated continuously as the project goes along. The list of changes can be viewed using the "edited" drop-down menu that's available above.

Community Bonding (May 4 - June 1)

Terracotta Back-End (June 1 - July 3)

Dash Integration (July 3 - July 31)

Final Touches (August 1 - August 24)

A buffer of 2 weeks has been taken to account for any unforeseeable absence on my end (about which I'll inform as early as possible).

gmajan commented 4 years ago

Abhineet, This is a good beginning but I hope you agree it needs work. Please discuss with @kaskou and you need to connect to @mfellows to get more details on what needs doing. It is very important to get clear deliverables so we can celebrate when you reach your milestones. Good luck!

abhineet97 commented 4 years ago

Thank you so much for your feedback @gmajan.

Yes, I agree that it need works. I'll keep on discussing with my mentors and will clarify the plan with the deliverables ASAP.

abhineet97 commented 4 years ago

Hello, @kaskou and @gmajan

I've updated the project plan and have now highlighted the deliverables more clearly. Please, let me know how I can improve it furture.

gmajan commented 4 years ago

Hi Abhineet, Looks good. I think you will be able to do more in August but let's revise that when we get to that point. Well done. Guy

kaskou commented 4 years ago

Hi abhineet, Good work and Looks good to me. But can you also add

Thanks

kaskou commented 4 years ago

Hi @abhineet97 , can you please add this as well to the plan

Thanks