Weekly Scrum #3 - November 20th #19

Open Kousha-Motazedian opened 11 months ago

Kousha-Motazedian commented 11 months ago
Kousha-Motazedian commented 11 months ago

What have I done this week? Finished work on the presentation and recorded video for the alternatives to ORM.

What will I do next week? Work on the templates for the front end. Issue: #21 PR: #20

What is holding me back? Nothing as of right now

momokaddour commented 11 months ago

What I did:

What will I do next week?

What is holding me back?

Bilalbc commented 11 months ago

What I did:

Researched alternatives to ORM for our presentation, specifically ObjectDB and jOOQ, and assisten in the implementation of 
ObjectDB into our project. Created slides and recorded our presentation demo.

What will I do next week?

complete overall testing of the milestone on completion, including integration and unit testing, as well as assist in the 
development of the front end templates using JS.

What is holding me back?

Nothing currently.

MattPorker commented 11 months ago

What I did: Finished working on the presentation and video for the alternatives to ORM What will I do next week: Work on templates and integration of backend system What is holding me back?: Nothing

AkshayVash1 commented 11 months ago

What have I done this week:

What will I do next week:

What is holding me back: