Major Steps

  1. Planning
    • [x] measure the roof
    • [x] assemble the bill of materials
    • [x] order the materials (Jul 12)
      • [x] solar equipment, related to #13
      • [x] metal roofing (Jul 23, 3-4 week lead time)
  2. Remove the solar array
    • [x] run conduit to SW roof (Jul 21)
    • [x] install combiner box and run wire to SW roof (Jul 22)
    • [x] set up rails on SW roof to receive panels (Jul 23)
    • [x] Remove the solar array (Jul 24-25)
  3. Tearoff
    • [x] get construction dumpster (Jul 30)
    • [x] mount safety anchor
    • [x] Tear off shingles and underlayment (Jul 31)
  4. Repair / Upgrade decking
    • [x] raise skylight curbs to 5-1/2" Remove skylights (Aug 1)
    • [x] replace plywood, as needed (Aug 4)
    • [x] nail schedule to IRC 2021 (6" in field, Aug 6)
  5. Install underlayment, 50 yr warranty
    • Grace Ice & Water Shield HT 3'x75', 10 rolls @ $235 4 mo. UV
      • side laps 3.5", end laps 6", roller the laps
    • [x] Sharkskin Ultra SA, 5 rolls @ $319, 12 mo. UV (Aug 9)
  6. [x] Install fascia wrap (Sep 7)
  7. [x] Install gutters (Sep 9)
    • Gutter 1: install end cap (on the ground)
      • silicone sealant, install cap, drill 2 holes per side and rivet, sealant inside seams
      • splice: 2 beads of sealant 3" from center, mate with gutter, drill 3 holes per side and rivet
      • install gutter on roof, pancake screws on 12" center
    • Gutter 2+: install 2 beads of sealant 3" from end, position in splice leaving 1/8" gap
      • drill 3 holes per side and rivet on sealant seam.
      • sealant on inside seam
    • Downspout Outlets
      • determine position, mark outline, drill hole with stepper bit, snip out hole
      • sealant around perimeter, install outlet, drill 3 holes per side and rivet
    • Straps: 24" spacing
      • drill hole in strap and gutter, rivet strap at front, pancake screw at back
  8. [x] Install gutter downspouts (Sep 10 & 11)
  9. Install starter trim
    • [x] joggle cleats along the eaves (Sep 10)
    • [x] install 8" strip of Ice & Water (200') along eaves, at 2" from edge (Sep 10)
    • [x] receiver trim along rake/gable, 1" from ridge, flush to eave, fasten 12" OC (Sep 11)
    • [ ] rake/gable trim cleats, fasten 12" OC
  10. Install metal panels
    • [x] square up the roof (3-4-5 📐), snap true lines at 3-9' intervals
    • [x] on each panel, fold the bottom tabs 180° and install backer rod
    • [ ] install the panels on the roof, one screw at ridge
    • install flashing around skylights
    • [ ] install gable trim, 6" overlap at seams, rivet to receiver trip @ 12" OC
  11. ridge cap
    • [ ] install z-bar closures
    • [ ] seal closures with butyl tape (3/16 x 7/8) and acrylic sealant
    • [ ] install ridge cap
  12. Reinstall the solar panels

References

msimerson commented 1 month ago

July 30th, 1 PM

9C5F5935-74F0-4A6D-B2AC-5A17D9557E41

July 31, 1 PM

IMG_5669

msimerson commented 1 month ago

August 7

IMG_5681